Milestone Payments with a Chinese Supplier: Deposits, Progress Payments and Retention
The way you structure payment matters as much as the price. How to split a China order into a deposit, progress payments and retention — and why the word 定金 changes everything.
Most buyers negotiate a Chinese supplier's payment terms the way they negotiate price: they focus on the first number and skim the rest. That is backwards. The structure of the payments — what you pay, when you release it, and what evidence unlocks each release — is what keeps your money attached to the work. A well-built schedule makes the supplier's incentive to perform line up with your incentive to pay, and it gives you a contractual lever to stop the money when the goods go wrong. China's Civil Code gives that structure real teeth, but only if the contract uses the right words.
Deposit, advance payment, and the word that changes everything
The first trap is linguistic, and it is expensive. Under the PRC Civil Code, a 定金 (deposit) is security for performance. Article 586 caps it at 20% of the principal contract price; Article 587 says that if the paying party fails to perform so that the contract's purpose cannot be achieved, the deposit is forfeited — and if the receiving party so fails, it must return the deposit double. Article 588 lets the non-breaching party elect between the deposit and liquidated damages when both are agreed. A 预付款 or 订金, by contrast, is merely part-payment of the price: refundable, with no forfeiture or double-return function. The practical rule is brutal in its simplicity — if you want forfeiture protection, the contract must say 定金, and the amount must stay within the 20% cap to keep that effect.
A milestone schedule that protects the buyer
The default in Chinese sourcing is a large up-front T/T payment, or a 30% deposit with the balance before shipment. You do not have to accept that. A stronger structure releases money in stages, each tied to something you can verify:
- Deposit (定金), up to 20% of the order, paid against a signed bilingual contract and proforma invoice — no more, because only the first 20% has deposit effect.
- A progress payment released only against verifiable evidence: raw materials purchased, production started, or a pre-production sample you have approved.
- A second progress payment against the pre-shipment inspection — a passing third-party report, not the supplier's own photos.
- The balance against shipping documents, and, on a large or new order, a retention of 5–10% withheld until acceptance and held through the warranty period.
Tie each release to evidence
A milestone without evidence is a promise. For each release, name the objective evidence that unlocks it: a material purchase invoice, a dated production report, a third-party inspection report with photographs, a bill of lading, an acceptance certificate. Pre-shipment inspection by an independent firm is the single most valuable gate, because it converts "the supplier says it is ready" into "an inspector measured it." Write the terms in a bilingual purchase or sales contract, and state the bank account details, the payment method (T/T, letter of credit, or another agreed instrument), and when title and risk transfer — the payment clause and the Incoterm must tell the same story.
Retention and the warranty window
Retention is the part most buyers skip and most regret skipping. A retention of 5–10%, released only after acceptance and after the warranty period runs, keeps a real incentive for the supplier to fix defects rather than disappear. Spell out the exact event and objective criteria for release, or the supplier will claim you are wrongfully withholding. On a first order with a new supplier, a lower deposit, tighter milestones and a larger retention are the rational defaults; as a relationship proves itself, the structure can loosen.
A supplier that insists on "100% T/T before production" is pricing in the risk that you will not pay — or that it will not deliver. If it cannot produce on a staged schedule against evidence, treat that as a red flag, not a negotiation detail. This content is general information and not legal advice.
None of this removes the need to verify the supplier before you pay — that is a separate step, and it should come first. Payment structure and supplier verification are the same decision from two angles: you are deciding how much of your money to put at risk, and when.